Rainwater Pump System Pre-Commissioning Checklist

Please fill out the below form and return to General Pump Company 48 hours prior to the day of commissioning. A technician will not be sent to site until the below checklist has been completed.

If the site is not ready for commissioning and the below points have not been checked, a futile commission fee of $380.00 + GST will be charged. Any additional works, time and components required to rectify incomplete installation will be charged accordingly

Please enable JavaScript in your browser to complete this form.
Company or Consumer
Pumps have been mounted and plumbed – each pump with check valve
Power supply is active and connected to main isolator in controller
Filtration equipment installed – UV globe & thimble fitted
Mains solenoid mounted in pipework and wired back to controller
Float switch is mounted in tank and pulled through conduit into controller
Water supply source is available to the pump system
All necessary conduit to the control panel is complete and wires pulled through
UV filter has adequate protection from the weather, and in a well-ventilated area